Generator & Auxiliary Engine Service
Ship service diesel generators demand continuous readiness. We execute in-situ or workshop overhauls for cylinder heads, crankshaft journals, camshafts, fuel injection systems, and charge air coolers across Tuzla shipyards and worldwide voyages.

Scope
- 10,000 and 20,000 hour scheduled major overhauls
- Alternator flexible coupling renewal and laser alignment
- Lubricating oil and jacket cooling water pump overhauls
- Governor overhaul, linkage calibration, and load sharing verification
- Camshaft timing check, bushing renewal, and valve lash tuning
How the job runs
- 1
Operational Audit
Exhaust temps, crankcase pressure, and baseline vibration checks.
- 2
Component Teardown
Cylinder heads, connecting rods, shells, and auxiliary drive units.
- 3
Precision Honing & Grinding
Valve vacuum hold tests, small-end bush sizing, and liner measurement.
- 4
Rebuild & Timing
Spill timing adjustment, bearing torqueing, and backlash calibration.
- 5
Step-Load Trials
Validation at 25%, 50%, 75%, and 100% electrical load profile.
Equipment we work onRepresentative
- Yanmar (EY, N, M series), Daihatsu (DK, DL, DE series)
- MAN B&W Holeby (L16/24, L21/31, L23/30, L28/32)
- Wärtsilä (Vasa 20, 26, 32), Caterpillar / MaK, Cummins, Scania
This list is representative. Send us your engine model and we will confirm the scope. Not an OEM authorisation.
Work in this service
Related guide articles
Questions
Can auxiliary engine overhauls be performed at sea?
Yes, provided the remaining generator sets maintain safe vessel operations and the Master/Superintendent approves voyage repair protocol.
How long does a complete 6-cylinder generator overhaul take?
Typically 3 to 5 working days on-board when required spare parts and consumables are staged on site.
Quote for this job
Tell us where the ship is and what failed; we'll review the scope and get back to you.